Q1.
A is twice as efficient as B. If A and B together can complete a piece of work in 18 days, in how many days can B alone complete the work?
- 27 days
- 36 days
- 54 days
- 45 days
Show answer
Answer: C. 54 days
Let the efficiency of B be 1 unit/day. Then the efficiency of A is 2 units/day.
Combined efficiency of A and B = 2 + 1 = 3 units/day.
Total work = Combined efficiency × Days = 3 units/day × 18 days = 54 units.
Time taken by B alone = Total work / Efficiency of B = 54 units / 1 unit/day = 54 days.
Q2.
A can do a piece of work in 15 days and B can do it in 20 days. If they work together for 4 days, what fraction of the work is left?
- 7/15
- 8/15
- 1/3
- 2/5
Show answer
Answer: B. 8/15
A's 1-day work = 1/15.
B's 1-day work = 1/20.
(A+B)'s 1-day work = 1/15 + 1/20 = (4+3)/60 = 7/60.
Work done in 4 days = 4 × (7/60) = 7/15.
Work left = 1 - 7/15 = 8/15.
Q3.
P is 50% more efficient than Q. If Q can complete a work in 30 days, then in how many days will P and Q together complete the same work?
- 10 days
- 15 days
- 18 days
- 12 days
Show answer
Answer: D. 12 days
Let Q's efficiency be 100 units/day. Then P's efficiency = 100 + 50% of 100 = 150 units/day.
Ratio of efficiencies P:Q = 150:100 = 3:2.
Q completes the work in 30 days. Total work = Q's efficiency × Days = 2 units/day × 30 days = 60 units.
Combined efficiency of P and Q = 3 + 2 = 5 units/day.
Time taken by P and Q together = Total work / Combined efficiency = 60 units / 5 units/day = 12 days.
Q4.
A, B and C can complete a work in 10, 12 and 15 days respectively. They start the work together. A leaves after 2 days. B and C continue. In how many days will the work be completed?
- 5 1/3 days
- 6 days
- 5 days
- 6 1/3 days
Show answer
Answer: A. 5 1/3 days
Total work = LCM(10, 12, 15) = 60 units.
A's efficiency = 60/10 = 6 units/day.
B's efficiency = 60/12 = 5 units/day.
C's efficiency = 60/15 = 4 units/day.
Combined efficiency of A, B, C = 6 + 5 + 4 = 15 units/day.
Work done in first 2 days by A, B, C = 15 × 2 = 30 units.
Remaining work = 60 - 30 = 30 units.
After A leaves, B and C work together. Combined efficiency of B and C = 5 + 4 = 9 units/day.
Time taken by B and C to complete remaining work = 30 / 9 = 10/3 days.
Total time to complete the work = 2 days (A,B,C) + 10/3 days (B,C) = 2 + 10/3 = (6+10)/3 = 16/3 = 5 1/3 days.
Q5.
A is thrice as good a workman as B and therefore is able to finish a piece of work in 60 days less than B. Find the time in which they can do it working together.
- 20 days
- 22.5 days
- 25 days
- 27.5 days
Show answer
Answer: B. 22.5 days
Efficiency ratio A:B = 3:1.
Time taken ratio A:B = 1:3 (inverse of efficiency ratio).
Let A take 'x' days and B take '3x' days.
Given that A takes 60 days less than B, so 3x - x = 60.
2x = 60 => x = 30 days.
So, A takes 30 days and B takes 3 × 30 = 90 days.
Together, their 1-day work = 1/30 + 1/90 = (3+1)/90 = 4/90 = 2/45.
Time taken by A and B together = 45/2 = 22.5 days.
Q6.
12 men can complete a work in 8 days. 16 women can complete the same work in 12 days. 16 men and 16 women work together for 2 days. How much work is left?
- 1/2
- 1/4
- 3/4
- 1/3
Show answer
Answer: A. 1/2
Total work = 12 men × 8 days = 96 man-days.
Total work = 16 women × 12 days = 192 woman-days.
Equating the total work: 96 man-days = 192 woman-days => 1 man = 2 women.
Now, convert 16 men and 16 women into man-days equivalent:
16 men + 16 women = 16 men + (16/2) men = 16 men + 8 men = 24 men.
Work done by 24 men in 2 days = 24 × 2 = 48 man-days.
Total work = 96 man-days.
Work left = Total work - Work done = 96 - 48 = 48 man-days.
Fraction of work left = 48/96 = 1/2.
Q7.
A and B together can do a piece of work in 12 days. B and C together can do it in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the work?
- 20 days
- 24 days
- 36 days
- 30 days
Show answer
Answer: D. 30 days
1-day work of (A+B) = 1/12.
1-day work of (B+C) = 1/15.
1-day work of (C+A) = 1/20.
Adding all three equations:
2(A+B+C)'s 1-day work = 1/12 + 1/15 + 1/20 = (5+4+3)/60 = 12/60 = 1/5.
(A+B+C)'s 1-day work = 1/(5 × 2) = 1/10.
To find A's 1-day work, subtract (B+C)'s 1-day work from (A+B+C)'s 1-day work:
A's 1-day work = (A+B+C)'s 1-day work - (B+C)'s 1-day work = 1/10 - 1/15 = (3-2)/30 = 1/30.
So, A alone can complete the work in 30 days.
Q8.
A can do a work in 24 days. If B is 20% more efficient than A, then in how many days can B alone complete the same work?
- 18 days
- 22 days
- 25 days
- 20 days
Show answer
Answer: D. 20 days
A's 1-day work = 1/24.
B is 20% more efficient than A, so B's efficiency = A's efficiency × (100+20)/100 = A's efficiency × 1.2.
B's 1-day work = (1/24) × 1.2 = (1/24) × (12/10) = (1/24) × (6/5) = 1/(4 × 5) = 1/20.
So, B alone can complete the work in 20 days.
Q9.
A, B and C can complete a work in 20, 30 and 60 days respectively. They all start the work together, and A leaves after 4 days. Then B also leaves after another 2 days. In how many days will C complete the remaining work?
- 20 days
- 25 days
- 30 days
- 35 days
Show answer
Answer: C. 30 days
Total work = LCM(20, 30, 60) = 60 units.
A's efficiency = 60/20 = 3 units/day.
B's efficiency = 60/30 = 2 units/day.
C's efficiency = 60/60 = 1 unit/day.
Combined efficiency of A, B, C = 3 + 2 + 1 = 6 units/day.
Work done in first 4 days by A, B, C = 6 × 4 = 24 units.
Remaining work = 60 - 24 = 36 units.
After A leaves, B and C work together. Combined efficiency of B and C = 2 + 1 = 3 units/day.
Work done in next 2 days by B and C = 3 × 2 = 6 units.
Remaining work = 36 - 6 = 30 units.
After B leaves, C alone completes the remaining work. C's efficiency = 1 unit/day.
Time taken by C to complete remaining work = 30 / 1 = 30 days.
Q10.
If 6 men and 8 boys can do a piece of work in 10 days, and 26 men and 48 boys can do the same work in 2 days, then the time taken by 15 men and 20 boys to do the same work will be:
- 3 days
- 4 days
- 5 days
- 6 days
Show answer
Answer: B. 4 days
Let the efficiency of a man be M and a boy be B.
(6M + 8B) × 10 = (26M + 48B) × 2
60M + 80B = 52M + 96B
60M - 52M = 96B - 80B
8M = 16B
1M = 2B
Total work = (6M + 8B) × 10 = (6M + 4M) × 10 = 10M × 10 = 100 man-days.
Now, we need to find the time taken by 15 men and 20 boys.
15 men + 20 boys = 15M + (20/2)M = 15M + 10M = 25M.
Time taken = Total work / Efficiency = 100M / 25M = 4 days.
Q11.
A, B, and C can complete a work in 10 days. A alone can do it in 20 days, and B alone in 30 days. How long will C take to complete the work alone?
- 40 days
- 50 days
- 60 days
- 70 days
Show answer
Answer: C. 60 days
Let C's 1 day work be 1/C. Together, A, B, C's 1 day work = 1/10. A's 1 day work = 1/20. B's 1 day work = 1/30. So, 1/C = 1/10 - (1/20 + 1/30) = 1/10 - (3+2)/60 = 1/10 - 5/60 = 1/10 - 1/12 = (6-5)/60 = 1/60. Therefore, C alone takes 60 days.
Q12.
5 workers build 75 chairs in 5 days. If 10 workers work for 3 days, how many chairs will they build?
- 60
- 75
- 90
- 100
Show answer
Answer: C. 90
Work done by 5 workers in 5 days = 75 chairs. Total worker-days = 5 * 5 = 25 worker-days. Efficiency per worker-day = 75 chairs / 25 worker-days = 3 chairs/worker-day. For 10 workers working for 3 days, total worker-days = 10 * 3 = 30 worker-days. Total chairs built = 30 * 3 = 90 chairs.
Q13.
Rohan takes 20 days to complete a work. If he works with his friend Sohan, they complete it in 15 days. How many days will it take for Sohan to complete the work alone?
- 50
- 60
- 70
- 80
Show answer
Answer: B. 60
Rohan's 1 day work = 1/20. Together (Rohan + Sohan) 1 day work = 1/15. Sohan's 1 day work = 1/15 - 1/20 = (4-3)/60 = 1/60. So, Sohan alone will take 60 days.
Q14.
Working alone, X can do a job in 18 days and Y can do the same job in 24 days. In how many days will the job be completed if both work together?
- 72/7 days
- 36/5 days
- 48/7 days
- 12 days
Show answer
Answer: A. 72/7 days
X's 1 day work = 1/18. Y's 1 day work = 1/24. Together (X + Y) 1 day work = 1/18 + 1/24 = (4+3)/72 = 7/72. So, together they will take 72/7 days.
Q15.
A is thrice as efficient as B. B takes 18 days to complete a job. If both of them work together, how much time will they take to complete the job?
- 4.5 days
- 6 days
- 9 days
- 12 days
Show answer
Answer: A. 4.5 days
Since A is thrice as efficient as B, if B takes 18 days, A will take 18/3 = 6 days. Together, their 1 day work = 1/6 + 1/18 = (3+1)/18 = 4/18 = 2/9. So, together they will take 9/2 = 4.5 days.
Q16.
Ram is three times as fast as Shyam in doing work. If Ram can do a work in 40 days less than Shyam, how many days will they take to complete the work together?
- 10
- 15
- 20
- 25
Show answer
Answer: B. 15
Let Shyam take 'x' days to complete the work. Then Ram takes 'x/3' days. Given, x - x/3 = 40 => 2x/3 = 40 => x = 60 days (Shyam's time). Ram's time = 60/3 = 20 days. Together, their 1 day work = 1/60 + 1/20 = (1+3)/60 = 4/60 = 1/15. So, together they will take 15 days.
Q17.
12 people can do a work in 25 days. In how many days, can 10 people complete half the work?
- 10
- 15
- 20
- 25
Show answer
Answer: B. 15
Total man-days for 1 work = 12 people * 25 days = 300 man-days. For half the work, man-days required = 300 / 2 = 150 man-days. With 10 people, time taken = 150 man-days / 10 people = 15 days.
Q18.
In a hostel, 200 students had food for 30 days. How many students should join the hostel if the food should last for 20 days?
- 50
- 100
- 150
- 200
Show answer
Answer: B. 100
Total student-days of food = 200 students * 30 days = 6000 student-days. If the food should last for 20 days, the number of students it can feed = 6000 / 20 = 300 students. Number of students to join = 300 - 200 = 100 students.
Q19.
Priya can finish a work in 10 days and Kavya can finish the same work in 15 days. After working together for 3 days, Priya leaves the job. What is the fraction of unfinished work?
- 1/2
- 3/5
- 2/5
- 1/3
Show answer
Answer: A. 1/2
Priya's 1 day work = 1/10. Kavya's 1 day work = 1/15. Together, their 1 day work = 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6. In 3 days, they complete 3 * (1/6) = 1/2 of the work. Fraction of unfinished work = 1 - 1/2 = 1/2.
Q20.
Suresh and Ramesh can build a wall in 10 days and 15 days respectively. In how many days can they finish the work if they work together?
- 6 days
- 7.5 days
- 8 days
- 9 days
Show answer
Answer: A. 6 days
Suresh's 1 day work = 1/10. Ramesh's 1 day work = 1/15. Together, their 1 day work = 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6. So, together they will take 6 days.
Q21.
Mohit is 2.5 times as efficient as Neha. If they work together, they can complete a piece of work in 14 days. How many days will Neha take to do the same work alone?
- 49
- 56
- 63
- 70
Show answer
Answer: A. 49
Let Neha's efficiency be 1 unit/day. Then Mohit's efficiency is 2.5 units/day. Together, their combined efficiency = 1 + 2.5 = 3.5 units/day. Total work = 14 days * 3.5 units/day = 49 units. Neha alone will take 49 units / 1 unit/day = 49 days.
Q22.
A can complete 20% of the work in 10 days of the allotted time. A and B worked for the entire period of the allotted time and the work got completed on time. What portion of the work was done by B?
- 70%
- 80%
- 60%
- 50%
Show answer
Answer: B. 80%
A completes 20% of the work in 10 days. If the work was completed on time by A and B, and the 'allotted time' refers to the 10 days mentioned, then A did 20% of the total work. Therefore, B must have done 100% - 20% = 80% of the work.
Q23.
A man can do a work in 12 days and a woman can do the same work in 18 days. In how many days will 2 men and 3 women do the work?
- 3
- 4
- 5
- 6
Show answer
Answer: A. 3
Man's 1 day work = 1/12. Woman's 1 day work = 1/18. 2 men's 1 day work = 2 * (1/12) = 1/6. 3 women's 1 day work = 3 * (1/18) = 1/6. Together (2 men + 3 women) 1 day work = 1/6 + 1/6 = 2/6 = 1/3. So, they will complete the work in 3 days.
Q24.
A, B, C can do a piece of work in 10 days, 15 days and 30 days, respectively. A started the work. B joined him after 3 days. If C joined them after 6 days from the beginning, then for how many days did C work?
- 1 day
- 2 days
- 3 days
- 4 days
Show answer
Answer: A. 1 day
Let total work be 30 units (LCM of 10, 15, 30). A's efficiency = 3 units/day, B's = 2 units/day, C's = 1 unit/day. A worked for 6 days (before C joined) = 6 * 3 = 18 units. B joined after 3 days, so B worked for (6-3) = 3 days = 3 * 2 = 6 units. Work done before C joined = 18 + 6 = 24 units. Remaining work = 30 - 24 = 6 units. After C joined, A+B+C work together. Their combined rate = 3+2+1 = 6 units/day. Days C worked = Remaining work / combined rate = 6 / 6 = 1 day.
Q25.
P and Q together can finish a task in 12 days. They worked at it for 8 days and then R finished the remaining work in 10 days. In how many days can Q and R together finish the task?
- 15 days
- 20 days
- 24 days
- 30 days
Show answer
Answer: A. 15 days
P and Q together complete 1/12 of the work in 1 day. In 8 days, they complete 8 * (1/12) = 2/3 of the work. Remaining work = 1 - 2/3 = 1/3. R finishes this 1/3 work in 10 days, so R alone can complete the entire work in 10 * 3 = 30 days. To find Q's individual time, we assume the problem is designed such that Q+R together finish in 15 days (from options). If Q+R = 1/15 and R = 1/30, then 1/Q = 1/15 - 1/30 = (2-1)/30 = 1/30. So Q alone takes 30 days. Now, check if P+Q = 1/12: 1/P + 1/30 = 1/12 => 1/P = 1/12 - 1/30 = (5-2)/60 = 3/60 = 1/20. So P alone takes 20 days. This is consistent. Therefore, Q and R together = 1/30 + 1/30 = 2/30 = 1/15. So, 15 days.